Exercise 7-Training Rollout Plan
-
OBJECTIVE OF THE PROJECT PLAN: A Plan to rollout the Training Schedule for the whole organization.
DESCRIPTION:
- Complexity: INTERMEDIATE Level
- Task Items: <~99 / ~6 months
- File Type: Template
- Domain: HR
- Project Management Phases: Initiation, Planning, Execution
- Key Concepts Learned: Resource Management, Using Work resources, Material resources and Cost resources, Effort Driven Tasks
SCENARIO:
You are the "General Manager - Human Resources (GM-HR)" of a Multi National Company - Manufacturers of high quality automobile spare parts.- Your organization is going to be certified for QS9000 company level certification in 18 months time.
- You have to provide the first set of Orientation Trainings to the management level officers of the entire organization.
- The key STAKEHOLDER of this project will be your own company.
- The key challenge will be to organize trainings across 10+ locations in India - and another 10 manufacturing locations worldwide.
Â
Some guidelines you have established:
- People, training material and training budgets will have to be carefully managed
- You intend to plan this over 4 Stages - Planning, Commencement, Implementation and Conclusion
- Communicate Plan early - so you can book resources time schedules
-------------------------------------------------
The WBS / Task list - notes- A plan completed about 60% has been given to you.
- You have to build out the rest as per guidelines:
- Complete Phases 3 and 4 - using your imagination to populate atleast 20 new tasks - both phases included
- WORK Resources have been created - make the Allocations
- Ensure no overallocations
- CREATE A NEW TEMPLATE FROM YOUR CHANGES
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-