      Exercise 7-Training Rollout Plan

      • OBJECTIVE OF THE PROJECT PLAN: A Plan to rollout the Training Schedule for the whole organization.


        DESCRIPTION:

        • Complexity: INTERMEDIATE Level
        • Task Items: <~99 / ~6 months
        • File Type: Template
        • Domain: HR
        • Project Management Phases: Initiation, Planning, Execution
        • Key Concepts Learned: Resource Management, Using Work resources, Material resources and Cost resources, Effort Driven Tasks


        SCENARIO:
        You are the "General Manager - Human Resources (GM-HR)" of a Multi National Company - Manufacturers of high quality automobile spare parts.

        1. Your organization is going to be certified for QS9000 company level certification in 18 months time.
        2. You have to provide the first set of Orientation Trainings to the management level officers of the entire organization.
        3. The key STAKEHOLDER of this project will be your own company.
        4. The key challenge will be to organize trainings across 10+ locations in India - and another 10 manufacturing locations worldwide.

         
        Some guidelines you have established:
        - People, training material and training budgets will have to be carefully managed
        - You intend to plan this over 4 Stages - Planning, Commencement, Implementation and Conclusion
        - Communicate Plan early - so you can book resources time schedules

        -------------------------------------------------
        The WBS / Task list - notes

        • A plan completed about 60% has been given to you.
        • You have to build out the rest as per guidelines:
          • Complete Phases 3 and 4 - using your imagination to populate atleast 20 new tasks - both phases included
          • WORK Resources have been created - make the Allocations
          • Ensure no overallocations
          • CREATE A NEW TEMPLATE FROM YOUR CHANGES

      • 2. Learning Objectives of this Section.mp4
      • Text

        2.1 OVERVIEW of Exercise 7 - Training Rollout Plan.txt

      • 3. Project Exercise 7 Training Rollout Plan.mp4
      • Other

        3.1 9.2 Project Exercise 7 - Training Rollout Plan.mpp

      • 4. Resource Management - Types of Resources.mp4
      • Other

        4.1 9.3 Resource Management - Types of Resources - BEGIN.mpp

      • 5. Managing Work Resources.mp4
      • Other

        5.2 9.4 Managing Work resources - BEGIN.mpp

      • Other

        5.1 9.4 Managing Work resources - FINISH.mpp

      • 6. Using Material Resources.mp4
      • Other

        6.1 9.5 Using Material resources - BEGIN.mpp

      • Other

        6.2 9.5 Using Material resources - FINISH.mpp

      • 7. Using Cost Resources.mp4
      • Other

        7.1 9.6 Using Cost Resources - BEGIN.mpp

      • Other

        7.2 9.6 Using Cost Resources - FINISH.mpp

      • 8. Understanding Costing Concepts.mp4
      • Other

        8.2 9.7 Understanding Costing Concepts - FINISH.mpp

      • Other

        8.1 9.7 Understanding Costing Concepts - BEGIN.mpp

      • 9. Effort Driven Scheduling.mp4
      • Other

        9.2 9.8 Effort Driven Scheduling - FINISH.mpp

        Restricted
      • Other

        9.1 9.8 Effort Driven Scheduling - BEGIN.mpp

      • Assignment

        Assignment to Exercise 7

    Skip Navigation

    Navigation

    • Home

      • SSML&D

        • Tags

        • Search

        • Calendar

        • ForumSite announcements

      • Courses

        • Project Management

          • SSM Process

          • Project Management Practices

            • M0-MP-TPM

            • M0-MP-MSP

              • Participants

              • General

              • Welcome & Introduction Exercise 1

              • Get the FUNDAMENTALS RIGHT!

              • Exercise 1-Microsoft Project Plan - Purchase New ...

              • Exercise 2-Test Plan for an eCommerce Site

              • IMPORTANT CONCEPTS

              • Exercise 3-Office Shift Project Plan

              • Exercise 4 - Summarize, Assignments and Linking

              • Exercise 5-Initiation, planning, execution

              • Exercise 6 - Overallocations, Lag and Lead, Advanc...

              • Formatting of Views

              • Exercise 7-Training Rollout Plan

                • File2.1 OVERVIEW of Exercise 7 - Training Rollout Plan...

                • File3.1 9.2 Project Exercise 7 - Training Rollout Plan...

                • File4.1 9.3 Resource Management - Types of Resources -...

                • File5.2 9.4 Managing Work resources - BEGIN.mpp

                • File5.1 9.4 Managing Work resources - FINISH.mpp

                • File6.1 9.5 Using Material resources - BEGIN.mpp

                • File6.2 9.5 Using Material resources - FINISH.mpp

                • File7.1 9.6 Using Cost Resources - BEGIN.mpp

                • File7.2 9.6 Using Cost Resources - FINISH.mpp

                • File8.2 9.7 Understanding Costing Concepts - FINISH.mpp

                • File8.1 9.7 Understanding Costing Concepts - BEGIN.mpp

                • File9.2 9.8 Effort Driven Scheduling - FINISH.mpp

                • File9.1 9.8 Effort Driven Scheduling - BEGIN.mpp

                • Assignment Assignment to Exercise 7

              • Exercise 8 - Commercial Office Construction

              • Exercise 9 - Product Marketing Campaign Launch

              • Exercise 10 - Learning Management System Implement

              • Exercise 10-Contd RESOLVING DIFFICULT PROBLEMS

              • Quiz

              • Animated navigation offAnimated navigation off

              • Data preferenceData preference

        • Common Training

          • Induction Training

          • HR Policy Induction

          • Role Based Training

        • Fundamentals

          • Commercial Fundamentals

          • Technical Fundamentals

          • Concept

          • Tools

          • Process fundamentals

        • Engineering Division

          • X-Force Software - Introduction

          • X-Force Software - Pro

          • X-Force Software - Advance

          • SSM Industry Solutions - Introduction

          • Wonderware - Introduction

          • Wonderware - Pro

          • Wonderware - Advance

            • Communication Drivers

          • Wonderware Industries Solution - Introduction

          • Wonderware Industries Solution - Pro

          • Aveva APM

          • Automation - Introduction

          • Automation - Basic

          • Automation - Medium

          • Automation- Advanced

          • Matrikon - Introduction

          • Matrikon - Pro

          • Matrikon - Advance

          • MDT Soft - Introduction

          • MDT Soft - Pro

          • MDT Soft - Advance

          • MasterClock - Introduction

          • MasterClock - Pro

          • AVEVA

        • Sales Division

          • SSM Corporate Introduction

          • X-Force Software Sales Introduction

          • Wonderware - Sales Introduction

          • Wonderware Industries Solution - Sales Introduction

          • Service Divisions - Sales Introduction

          • Automation - Sales Introduction

          • Matrikon - Sales Introduction

          • MDT Soft - Sales Introduction

          • MasterClock - Sales Introduction

          • Aveva APM Sales

        • SSM Solutions

          • Energy Monitoring

          • Utility Management

        • IT Division

          • IT and Networking

          • Server Softwares

          • IT Solutions

          • Operating Systems

        • Software Division

          • Basics of Programming

          • Languages

            • C# Development

            • VB.NET

            • Java

            • Python

            • Visual Basic

          • Platform

          • Database Access

          • Software Testing

          • DevOps

        • Solution Design

          • IT and Networking

          • X-Force Software - Solution Design

          • Wonderware - Solution Design

          • Wonderware Industries Solution - Solution Design

          • Automation - Solution Design

          • Matrikon - Solution Design

          • MDT Soft - Solution Design

          • MasterClock - Solution Design

          • Common Solutions

        • Technical Management

          • SSM Technical Management

        • Personal Development

        • X-Force Products

          • AIMS

          • EMS

          • Historian

          • DocX

        • Automation

        • Wonderware

          • Alpana Dashbaord

          • APM

          • Common

          • GISize

          • Historian

          • InBatch

          • MES

          • Operations Integration

          • QIAnalytics

          • Skelta

          • System Platform

        • Wonderware Solutions

          • Line Performance

          • Water Network Optimization

          • Smart City

          • Energy Performance for Mfg

          • Label Ensurance

        • Products

          • Matrikon

          • Time Synch

          • Firewalls

        • Moodle

        • SSM SOP

          • Business Processes

          • Automation

          • HR Process

          • IT Processes

        • Screening Test

        • Aptitude Quiz